|
Paint Booth Cleaning - This task included the
removal of paint overspray that had accumulated on interior
surfaces and conveyor track of the facility paint booth. In
some areas, the layers of deposited paint exceeded a thickness of 4
inches.
In order to achieve complete removal, Allied systematically
froze the paint utilizing dry-ice (CO2). The
dry-ice decreased the elasticity of the paint build-up, rendering
it brittle and easily fractured. Allied then employed powered
hammers to break and remove the paint.
The waste material was drummed and properly disposed of as
non-hazardous waste.
X-ray Booth Trench Cleaning - In addition
to scheduled project work, Allied responded to an issue discovered
during shutdown activities.
Trade workers installing utilities in the manufacturing area
discovered a trench containing trace quantities of machining
coolant and metals debris. To be proactive and
safety-conscious, the client asked Allied to clean the trench so
that it could be safely occupied by workers.
Allied responded immediately, deploying a mobile wash truck and
vacuum truck to the facility. Allied assisted in the removal
of the trench covers by utilizing a magnetic crane. The
interior surfaces of the trench were then power washed and all
materials and wash water were evacuated from the trench utilizing a
vac-truck.
The collected waste was transported to an offsite facility for
disposal as non-hazardous waste.
Dust Removal - Facility operations result in
the creation of fine particulate (dust), which accumulates on the
structural ceiling rafters, suspended electrical bus bars, the tops
of furnaces and surfaces of other equipment. The client regularly
removes the accumulated dust to prevent potential safety and
quality issues.
To prevent potential electric shock while working near bus bars
and facility lights, power to the manufacturing area was turned off
and the Allied technicians used generators to power portable
lights, vacuums and other necessary equipment. The project was
completed during night shifts so that the daytime work of other
trades would not interrupted.
Allied utilized a total of seven articulating boom lifts to
access the affected areas. Hand tools and filtered vacuums were
used to remove accumulated dust from horizontal surfaces throughout
the manufacturing area. The project required the use of proper PPE
(protective suits, respirators and fall-protection harnesses). In
addition, lock-out/tag-out procedures were strictly followed to
ensure that electrical systems and manufacturing equipment remained
de-energized throughout the project.
Allied successfully completed all required industrial cleaning
activities safely, and within all time and budgetary
constraints.
|